Eversource to Perform Maintenance

Eliot & Newington
Wood Transmission Structure

As part of our everyday effort to deliver reliable energy to our customers and communities, we are preparing to perform maintenance on existing wood transmission structures in Newington and Eliot.  This work is a continuation of maintenance work from last year.  With the helicopter work complete, the remaining work necessary to complete the project will begin in the coming weeks on the  power line corridor that extends from Gosling Road in Newington, NH to Stacy Lane in Eliot, ME.

I have included some details below, in addition to the start of construction letter (see attachment below) that is being mailed to nearby property owners.   

3176 System Grounding Program 

Newington
SCHEDULE: September 2019 – Winter of 2019/2020
SCOPE: Installing structure hardware including ground rings and counterpoise
LOCATION:  Gosling Road
CONTRACTOR:  Michels Power  

Eliot, ME
SCHEDULE: August 2019 – Winter of 2019/2020
SCOPE: Installing structure hardware including ground rings and counterpoise
LOCATION:  Pleasant Street, Route 103, Leach Road, State Road, Bolt Hill Road, Beech Road, Bradstreet Lane, Depot Road, Cedar Road, Stacy Lane
CONTRACTOR:  Michels Power  